· Continued with the Meter Replacement Program, 12 Large meters were replaced.
· Continued with the valve “Exercising” Program, 389 of the City’s 1,400 valves were exercised and minor repairs were performed.
· Continued to work with West Basin Municipal Water District to supply Reclaimed Water to El Segundo customers, resulting in a 50% reduction in purchases of MWD imported potable water.
· Flushed system dead-end water mains quarterly.
· Flushed and tested 80 fire hydrants.
· Distributed Annual Consumer Confidence Report.
· Installed or inspected the installation of 25 new service connections and 5,000 feet of water main.
· Obtained, processed and billed 27,000 meter reads.
· Performed required water sampling which met or exceeded water quality standards set by the Department of Health Services.
· Repaired 8 Broken water Mains.