Time Limit for Refund Claims:

Plan Check Refunds: A claim for refund may be submitted within one year of the plan check submittal date. See below for amount of plan check fees that can be refunded. 

Permit Refunds:  A claim for refund may be submitted within one year of the last inspection date. 

 

Amount of Refund: 

All Plan Checks: Once a plan check review has commenced, any plan check-related fees are non-refundable. 

Building and Grading Permit Refunds: Up to 80% of the Building Permit fee and the Grading Permit fee are refundable. Other check fees related to check permits including retention fees, surcharges, etc. are eligible for a full refund. Refund amounts will be based on the percentage of work completed and inspected. 

Mechanical, Electrical, and Plumbing Permit Refunds: The permit issuance fee is non-refundable. Other fees  related to check permits are eligible for a full refund. Refund amounts will be based on the percentage of work completed and inspected. 

 


 

Please resolve the captcha.

Loading...
For further questions, please contact Venus Wesson, Senior Administrative Specialist at vwesson@elsegundo.org.